Project Description
Following financial close in 2005, three Healthy Living Centres have been successfully completed and handed over to the client. Our partners for the initial Medway LIFT schemes were:
|
Senior Funder
Sub Debt / Equity
Contractor
FM Provider |
Barclays Bank Plc
Barclays European Infrastructure Fund
Rydon Construction Ltd
Rydon Maintenance Ltd |
Lordswood Community Healthy Living Centre, Sultan Road, Lordswood, ME5 8TJ

Rainham Healthy Living Centre, High Street, Rainham, ME8 8AA

Rochester Community Healthy Living Centre, Delce Road, Rochester, ME1 2EL

|
| |
|
Project Profile
Financial Close
Client |
Medway LIFT – Tranche 2
3 June 2009
Medway PCT |
Project Description
Following the successful financial close of Tranche 1 in 2005, Medway LIFTCo successfully negotiated the Balmoral Gardens scheme. Our partners for the Tranche 2 Medway LIFT scheme are:
|
Senior Funder
Sub Debt / Equity
Contractor
FM Provider |
Aviva
Predominantly by Barclays Private Equity, as well as Medway PCT & CHP
Rydon Construction Ltd
Rydon Maintenance Ltd |
Balmoral Gardens Healthy Living Centre, Gillingham

|